Project Owner: B2Gold Namibia
Years of delivery: 2013-2014
Location: Namibia
Manufactured and delivered: more than 2,500 tons of steel structures.
46 tanks (including ten agitator tanks with a capacity of 3,472 cubic meters each with a wall thickness of 16 mm and a height of 18 m) as part of the construction of the Otjikoto Gold Mine.
The products were delivered by railway transport on specialized platforms to the port of St. Petersburg, then loaded on two sea vessels and shipped to Africa. Steel Structures Design was developed in accordance with the technical specifications of an Austrian design company.
Gold Recovery Factory, Otjikoto Mine (Namibia)
Project Owner: B2Gold Namibia
Years of delivery: 2013-2014
Location: Namibia
Manufactured and delivered: more than 2,500 tons of steel structures.
46 tanks (including ten agitator tanks with a capacity of 3,472 cubic meters each with a wall thickness of 16 mm and a height of 18 m) as part of the construction of the Otjikoto Gold Mine.
The products were delivered by railway transport on specialized platforms to the port of St. Petersburg, then loaded on two sea vessels and shipped to Africa. Steel Structures Design was developed in accordance with the technical specifications of an Austrian design company.
Years of delivery: 2013-2014
Location: Namibia
Manufactured and delivered: more than 2,500 tons of steel structures.
46 tanks (including ten agitator tanks with a capacity of 3,472 cubic meters each with a wall thickness of 16 mm and a height of 18 m) as part of the construction of the Otjikoto Gold Mine.
The products were delivered by railway transport on specialized platforms to the port of St. Petersburg, then loaded on two sea vessels and shipped to Africa. Steel Structures Design was developed in accordance with the technical specifications of an Austrian design company.